This week we started construction of the bunkhouse, between the The Lupine and The Wild Rose. Denison had poured the concrete into for the footers already and we were able to begin actual building. However, the project got held up on the first day as we had trouble getting the brackets on the concrete footers and had to make the trip to Phillipsburg for more parts. We did get a full day of building on Wednesday and completed the supporting beems as well as the framing for the floor boards. Right now Denison is thinking of naming the new building the "Bear Den" which is fitting, but feel free to leave ideas for other names in the comment section.
This is where we started Wednesday
Supporting beams go into place
Denison precariously placing I-beams 15' off the ground
Starting to visualize the third structure